Papua food and energy estate (Indonesia)
- Press and investigations Kompas: Reported the project criticised as triggering deforestation, with 486,939 ha of forest released. Kompas
- Communities and civil society Mighty Earth: More than 50,000 ha cleared in Merauke. Mighty Earth
- Government and regulators Government of Indonesia: Reported as saying it was ready to reforest. Kompas
Indonesia declared a food and energy project in Merauke, South Papua, a National Strategic Project in 2024. Sources put its size at between 1.2 million and over 2 million hectares, and report forest clearing with military participation.
As reported by Kompas, October 2025. Sources give the overall project area as between 1.2 million and over 2 million hectares.
Status As of October 2025: forest release and military-assisted clearing reported in Merauke; no court ruling or independent evaluation found.
- Ten companies holding recommendation letters for forest release — Recommended access to 541,094 ha of forest-estate land. Project Multatuli
- Sugar and bioethanol investors — Named in the sources reviewed as investors in the project.
- Malind, Maklew, Yei and Khimaima communities — Customary (adat) lands affected. Kompas
- Forest of Merauke — 486,939 ha released; more than 50,000 ha cleared according to Mighty Earth. Kompas
What happened
In 2024 Indonesia declared its Merauke food and energy project in South Papua a National Strategic Project (PSN). Sources describe its area as between 1.2 million and more than 2 million hectares; Mongabay, citing the research group CELIOS, reported a project of 2 to 3 million hectares in December 2024.
Project Multatuli, citing the Jakarta Post and the advocacy group Pusaka, reported that ten companies had received recommendation letters for the release of a total of 541,094 hectares of forest from the forest estate, and that in July 2024 a ministerial decision opened 13,540 hectares, including protected forest, to food infrastructure linked to defence.
Kompas reported in October 2025 that 486,939 hectares of forest had been released for Merauke and that battalions of the Indonesian military (TNI) were clearing land; the figures in the sources reviewed are five battalions and at least 2,000 soldiers. The Jakarta Post reported in March 2025 that concerns had been raised about the military's role in the project.
Mighty Earth, an advocacy group, reported that more than 50,000 hectares had been cleared in Merauke. Mongabay's December 2024 report described plans for about 2 million hectares of sugarcane and bioethanol and said indigenous consent had not been obtained.
The sources reviewed describe the affected customary (adat) lands as those of the Malind, Maklew, Yei and Khimaima peoples.
- 2024Merauke food and energy project declared a National Strategic Project; July: ministerial decision opens 13,540 ha, including protected forest, to defence-linked food infrastructure
- 2024December: Mongabay reports a 2 to 3 million hectare project and the risk of a carbon backfire from sugarcane clearing
- 2025March: Jakarta Post reports concerns over the TNI's role. October: Kompas reports 486,939 ha of forest released and TNI battalions clearing land
What was said
Where accounts differ
Each party's account, side by side, with its source. The record does not settle these points; it shows them.
Reported the project criticised as triggering deforestation, with 486,939 ha of forest released.
KompasIndigenous consent was not obtained for the planned sugarcane and bioethanol area.
MongabayHow it looked
Shown
- Presented as 'food and energy sovereignty'.Indonesian government framing, as summarised in the sources reviewed · Kompas
Recorded
- 486,939 ha of forest released for Merauke; TNI battalions clearing land; customary lands affected (Kompas, October 2025).
- Ten companies received recommendation letters for release of 541,094 ha of forest; a July 2024 ministerial decision opened 13,540 ha, including protected forest, to defence-linked food infrastructure.
- More than 50,000 ha cleared in Merauke, according to Mighty Earth.
Who gained
Reached nature or the ground
Gained elsewhere
Responses on record
- Government of Indonesia (October 2025): Kompas headline reports the government saying it was ready to carry out reforestation, in response to criticism that the project triggers deforestation. · Kompas
In court and with insurers
Lawsuits and rulings
Insurers
What nature saw
Nature's report opens this page. Below: further outcomes measured on the ground.
What we don't know
Nature
- Disputed Is the Merauke project driving deforestation?
Court
- None on record No court case on record.
Accounts
- Disputed Was indigenous consent obtained?
Record
- None on record Project area: sources give between 1.2 million and over 2 million hectares (Project Multatuli) and 2 to 3 million hectares (Mongabay/CELIOS); no single official figure is cited.
- Insufficient Reported but not independently verified: the July 2024 ministerial decision opening 13,540 ha, and that the customary owners (Malind, Maklew, Yei, Khimaima) are not legally recognised.
- None on record Indonesia received a results-based forest payment and later large-scale clearing began in Merauke; no source on record establishes a causal link.
Did the harm stop?
Clearing was reported as continuing as of October 2025; no halt is on record in the sources reviewed.
Who paid?
Customary landowners and the forest, according to the sources reviewed; no compensation is on record.
Sources
Press and investigations
- PSN Merauke Dikritik Picu Deforestasi, Pemerintah Bilang Siap ReforestasiKompas · 2025-10-21
- Concerns raised over TNI's role in Papua food estateThe Jakarta Post · 2025-03-01
- Merauke food estate (citing Jakarta Post and Pusaka)Project Multatuli · 2024
Communities and civil society
- Food estate projects in IndonesiaMighty Earth · 2025
Connected cases
- Corio, ABP and forest land investments (Netherlands) Netherlands · 2000–2021
- Transnational Institute (TNI) (NGO) — here: Indonesian military; reported clearing land; there: NGO; author of the 2013 briefing
- EU Deforestation Regulation delays and trade pressure European Union · 2022
- Government of Indonesia (Government) — here: Declared the project a National Strategic Project; there: Led joint letters
- Indonesia reopened sea sand exports in 2023; Supreme Court annulled them in 2025 Indonesia · 2023–2025
- Government of Indonesia (Government) — here: Declared the project a National Strategic Project; there: issued PP 26/2023 and the export rules
- Indonesia reopens sea-sand exports on a 17.66 billion m3 potential estimate Indonesia · 2023
- Government of Indonesia (Government) — here: Declared the project a National Strategic Project; there: reopened sea-sand exports under PP 26/2023
- Indonesia returns 883 of 2,194 flagged waste containers Indonesia · 2018–2019
- Government of Indonesia (Government) — here: Declared the project a National Strategic Project; there: Government that returned the flagged containers
- Indonesia's 2025 mining law change opens mining areas to religious groups without tender Indonesia · 2025
- Government of Indonesia (Government) — here: Declared the project a National Strategic Project; there: Lawmakers who passed the revision
- Indonesia's forest moratorium: ministry cited 38% less clearing, Greenpeace disputed it Indonesia · 2011–2019
- Government of Indonesia (Government) — here: Declared the project a National Strategic Project; there: imposed the moratorium; ministry reported the 38% figure
- Indonesia's H5N1 sample withholding and the WHO PIP Framework Indonesia · 2007–2026
- Government of Indonesia (Government) — here: Declared the project a National Strategic Project; there: Withheld H5N1 samples
- Indonesia's Nusantara capital faces funding gap as Jakarta keeps sinking Indonesia · 2019
- Government of Indonesia (Government) — here: Declared the project a National Strategic Project; there: Plans and funds the new capital
- Jakarta evictions, Ciliwung normalisation and the Giant Sea Wall Indonesia · 2014–2025
- Government of Indonesia (Government) — here: Declared the project a National Strategic Project; there: Central government; approved the Giant Sea Wall in 2025
- Raja Ampat nickel licences revoked Indonesia · 2025
- Government of Indonesia (Government) — here: Declared the project a National Strategic Project; there: Revoked four of five nickel permits
- Rinca island work in Komodo National Park continued after UNESCO asked for a halt Indonesia · 2020–2021
- Government of Indonesia (Government) — here: Declared the project a National Strategic Project; there: runs the 10 New Balis tourism programme
- Trade rules curb green industrial policy; WTO rules against Indonesia nickel ban Global · 2013–2026
- Government of Indonesia (Government) — here: Declared the project a National Strategic Project; there: Respondent in the nickel export ban case; complainant in the palm oil case
- WTO panel backs EU on palm biofuel rules in Malaysia case Global · 2025
- Government of Indonesia (Government) — here: Declared the project a National Strategic Project; there: Complainant in the Indonesia case
- WTO panel found Indonesia's raw nickel export ban breached rules Indonesia · 2020–2022
- Government of Indonesia (Government) — here: Declared the project a National Strategic Project; there: Imposed the ban and appealed the panel ruling