Who gains from saving nature
Ledger 1 : 33 — For each dollar financing nature-based solutions in 2023, about $33 financed activities harmful to nature. (UNEP)
Cases / Protected area / relocation · United States · 2000–2026

Comprehensive Everglades Restoration Plan (Florida): cost estimates, spending and National Academies reviews

Nature's voice · report
FY 2020 dollars; projected over about 50 years from authorization 23.2 billion US dollars were budgeted in my name. No one has measured what reached me.
Did nature suffer? Not measured. Accounts differ ↓
Not on record
  • The record does not name which of my species, waters, soils or forests were harmed.
What the record lacks: 3 none on record · 1 not measured · 3 disputed · 1 unclear See the gaps
Accounts of the harm differ
Whether construction should proceed before the phosphorus limit is met
  • Government and regulators US Army Corps of Engineers (as reported by CRS): No federal investment in CEPP North infrastructure until the effluent limit is met. Congressional Research Service
  • Government and regulators State of Florida (as reported by CRS): Proceeding with CEPP North construction before an attainment determination. Congressional Research Service

Congress approved the Comprehensive Everglades Restoration Plan in 2000 as a framework for the federal government and Florida to restore the Everglades, originally over 50 projects over 30 years at US$8.2 billion. The latest estimate in the sources is US$23.2 billion over about 50 years; through FY 2024 the federal government spent US$3.2 billion and Florida US$2.8 billion on CERP construction. National Academies reviews record progress and unresolved water-quality and reporting gaps.

US$23.2 billion estimateLatest projected total cost of the Comprehensive Everglades Restoration Plan
CRS (January 2025), citing the most recent report to Congress: about 50 years from authorization, in FY 2020 dollars (US$26.9 billion in FY 2023 dollars). The original 2000 estimate was US$8.2 billion in FY 2000 dollars.

Status As of January 2025: the projected cost is US$23.2 billion over about 50 years; seven CERP projects were under construction in FY 2024 and assessment of attainment of the phosphorus effluent limit was due to begin in 2026.

What?
A federal and Florida framework of Everglades restoration projects approved in 2000, originally over 50 projects over 30 years, now projected at about 50 years. Congressional Research Service
Where?
The Everglades and the south Florida ecosystem, including Lake Okeechobee and Biscayne Bay. Congressional Research Service
When?
Approved by the Water Resources Development Act of 2000; National Academies reviews biennially since 2004; tenth review released 1 October 2024; phosphorus limit assessment to begin in 2026. National Academies of Sciences, Engineering, and Medicine
Who?
Gained
None on record
Lost
None on record
Harmed
None on record
Why?
The ecosystem had declined to approximately half its historical size by the close of the 1900s, and the Academies describe its water quality, quantity, flow and distribution as dramatically degraded. Congressional Research Service
How?
The Corps and Florida build and operate storage, treatment and conveyance projects, sharing costs; the Corps requires the phosphorus effluent limit to be met before federal investment in CEPP North infrastructure. Congressional Research Service
5 of 6 questions answered from the record · open: who

What happened

The record, in order.

The Water Resources Development Act of 2000 approved the Comprehensive Everglades Restoration Plan (CERP), described by the Congressional Research Service (CRS) as "a framework under which the federal government and the State of Florida are attempting to restore the Everglades". CRS wrote that by the close of the 1900s the ecosystem "was approximately half its historical size". GAO described the plan in September 2000 as "a conceptual framework for improving the quality, quantity, timing, and distribution of water", with 24 of its 66 projects aimed at water quality, and recorded the Corps of Engineers' then-current estimate at US$7.8 billion, shared equally by the federal government and Florida. GAO warned of "too many uncertainties to estimate" the cost of future water quality projects and recommended that the Corps add a means of reporting cumulative changes in cost and progress to Congress.

CRS recorded the estimates over time (Table 1 of its October 2017 report): US$8.2 billion in the original 1999 estimate, US$10.9 billion in the 2004 update, US$13.5 billion in 2009 and US$16.4 billion in 2014. In January 2025 CRS wrote that the most recent report to Congress "projected CERP would take approximately 50 years from its authorization to implement at a total cost of $23.2 billion" (FY 2020 dollars), "due to inflation, changes in project scope and schedule, and new project authorizations", against an original plan of over 50 projects over 30 years at US$8.2 billion (FY 2000 dollars). CRS wrote that none of the original estimated completion dates in the conceptual plan had been met as of the end of 2016. It recorded that, through FY 2024, the federal government had spent US$3.2 billion and the State of Florida US$2.8 billion on CERP construction projects (nominal dollars, from cost-share transparency reporting), and that the federal government had spent approximately US$1.0 billion on non-CERP construction projects. CRS noted that the spending figures are nominal and that the cost estimates use different base years, so they are not directly comparable.

Project status in FY 2024, as listed by CRS, included two Corps projects completed or partly completed (C-111 Spreader Canal Western; Site 1 Impoundment phase 1), seven under construction (including Picayune Strand, Indian River Lagoon-South, C-43 West Storage Basin Reservoir and the Central Everglades Planning Project), three awaiting construction and three studies in progress. CRS wrote that "USACE has specified that no federal investment in CEPP North infrastructure can occur until the effluent limit is met", that the State of Florida was proceeding with CEPP North construction before an attainment determination, and that assessment of attainment of the phosphorus effluent limit was required to begin in 2026.

The National Academies have reviewed CERP biennially under the 2000 Act. As summarised in the Tenth Biennial Review (released 1 October 2024), the second review (2008) found "no CERP projects have been completed to date"; the third (2010) wrote that the goals "will be enormously costly and will take decades at least"; the eighth (2020) found progress assessments limited by weak monitoring; the ninth (2022) found that "record funding levels had accelerated" implementation "to a remarkable pace". The tenth review's summary reported "record-high levels of federal and state funding" in FY 2022 and FY 2023, six CERP projects under construction, one CERP project and two major components complete and another nearly finished, a 75 percent reduction in Melaleuca-dominated area, and total phosphorus concentrations in stormwater treatment area outflows trending downward, with only STA-3/4 currently meeting the water quality-based effluent limit. It also wrote that the "greatest danger is making no attempt to plan for climate change" and that CERP has no centralized multi-agency reporting mechanism.

  1. 1999Original CERP cost estimate of US$8.2 billion (FY 2000 dollars; CRS table)
  2. 2000Congress approves CERP in the Water Resources Development Act of 2000; GAO reports the Corps' US$7.8 billion estimate and recommends reporting of cumulative cost changes (20 September)
  3. 2004CERP cost update of US$10.9 billion
  4. 2008National Academies second biennial review: no CERP projects completed to date
  5. 2009CERP cost update of US$13.5 billion
  6. 2014CERP cost update of US$16.4 billion
  7. 2016As of the end of FY 2016 the federal government had provided in excess of US$1.2 billion for CERP; none of the original estimated completion dates met
  8. 2022National Academies ninth review: record funding levels accelerated implementation to a remarkable pace
  9. 2024National Academies tenth biennial review released (1 October); through FY 2024 federal spending of US$3.2 billion and Florida spending of US$2.8 billion on CERP construction (CRS)
  10. 2025CRS reports a projected US$23.2 billion cost over about 50 years (14 January)
  11. 2026Assessment of attainment of the phosphorus effluent limit required to begin

What was said

Claims, in the words of those who made them.

“a conceptual framework for improving the quality, quantity, timing, and distribution of water”

“too many uncertainties to estimate”

“will be enormously costly and will take decades at least”

“record-high levels of federal and state funding”

“greatest danger is making no attempt to plan for climate change”

“USACE has specified that no federal investment in CEPP North infrastructure can occur until the effluent limit is met”

Where accounts differ

Each party's account, side by side, with its source. The record does not settle these points; it shows them.

How much the plan costs and how long it takes
Government and regulators
GAO (2000), citing the Corps

Current estimate of US$7.8 billion, shared equally by the federal government and Florida; changes could increase the total.

US General Accounting Office (now GAO)
Government and regulators
Congressional Research Service (2025)

US$8.2 billion over 30 years at the outset (FY 2000 dollars); latest projection US$23.2 billion over about 50 years (FY 2020 dollars), due to inflation, changes in scope and schedule and new project authorizations.

Congressional Research Service
Whether construction should proceed before the phosphorus limit is met
Government and regulators
US Army Corps of Engineers (as reported by CRS)

No federal investment in CEPP North infrastructure until the effluent limit is met.

Congressional Research Service
Government and regulators
State of Florida (as reported by CRS)

Proceeding with CEPP North construction before an attainment determination.

Congressional Research Service

How it looked

What was shown, beside what was recorded.

Shown

  • The plan described as "a framework under which the federal government and the State of Florida are attempting to restore the Everglades", originally over 50 projects over 30 years at US$8.2 billion.
    Congressional Research Service · Congressional Research Service
  • Restoration described as moving at "a remarkable pace" on record funding.
    National Academies, ninth biennial review (2022), as summarised in the tenth review · National Academies of Sciences, Engineering, and Medicine

Recorded

  • Cost estimates in CRS tables and text: US$8.2 billion (1999), US$10.9 billion (2004), US$13.5 billion (2009), US$16.4 billion (2014), US$23.2 billion (latest, FY 2020 dollars).
  • Through FY 2024: federal spending of US$3.2 billion and Florida spending of US$2.8 billion on CERP construction projects (nominal dollars).
  • National Academies (2008): no CERP projects completed to date. National Academies (2024): one CERP project and two major components complete, six under construction.
  • National Academies (2024): only STA-3/4 currently meets the water quality-based effluent limit for phosphorus; a 75 percent reduction in Melaleuca-dominated area.
  • No source reviewed gives a system-wide measure of ecological recovery (flows, wildlife) attributable to CERP.

In nature's name

What was promised in nature's name, the money that moved, and what was measured.

Promised

  • “a framework under which the federal government and the State of Florida are attempting to restore the Everglades” — Congressional Research Service, describing the plan approved in the Water Resources Development Act of 2000 (14 January 2025) Congressional Research Service
  • “a conceptual framework for improving the quality, quantity, timing, and distribution of water” — GAO, describing the Corps of Engineers' plan (20 September 2000) US General Accounting Office (now GAO)

Money moved in nature's name

WhatKindAmountPeriod
Projected total cost of CERP, latest report to Congress
US Army Corps of Engineers and State of Florida (cost-shared)
Congressional Research Service
Budget$23.2bn estimateprojected
Original estimate of CERP total cost
US Army Corps of Engineers and State of Florida (cost-shared)
Congressional Research Service
Budget$8.2bn estimate2000 estimate
Corps' estimate of plan cost
US Army Corps of Engineers
US General Accounting Office (now GAO)
Budget$7.8bn estimate2000
Federal spending on CERP construction projects
US federal government
Congressional Research Service
Spent$3.2bnthrough FY 2024
State of Florida spending on CERP construction projects
State of Florida
Congressional Research Service
Spent$2.8bnthrough FY 2024
Federal spending on non-CERP construction projects
US federal government
Congressional Research Service
Spent$1bn estimatethrough FY 2024

What was measured

Not measured

The National Academies' reviews, requested by Congress and independent of the Corps, report project-level results (a 75 percent reduction in Melaleuca-dominated area; downward trends in phosphorus concentrations in stormwater treatment area outflows, with only STA-3/4 meeting the limit) and one CERP project and two major components complete. The sources reviewed give no system-wide measurement of ecological recovery attributable to CERP, and the summary states that CERP has no centralized multi-agency reporting mechanism.

Melaleuca-dominated area
75 percent reduction
National Academies tenth review summary; Melaleuca eradication project National Academies of Sciences, Engineering, and Medicine
Stormwater treatment areas meeting the phosphorus effluent limit
Only STA-3/4
National Academies tenth review summary; outflow concentrations trending downward National Academies of Sciences, Engineering, and Medicine
Projects complete
One CERP project and two major components; six CERP projects under construction
National Academies tenth review summary (2024); in 2008 no CERP project had been completed National Academies of Sciences, Engineering, and Medicine

Operation Ongoing · Seven CERP Corps projects under construction in FY 2024 (CRS). Congressional Research Service

Findings on record

  • Official audit US General Accounting Office (GAO) (2000-09-20) · GAO T-RCED-00-297, Comprehensive Everglades Restoration Plan: “has not, however, included a means for reporting” US General Accounting Office (now GAO)
  • Official audit National Academies, second biennial review (as summarised in the tenth review) (2008) · Progress Toward Restoring the Everglades: The Second Biennial Review - 2008: “no CERP projects have been completed to date” National Academies of Sciences, Engineering, and Medicine
  • Official audit National Academies of Sciences, Engineering, and Medicine (2024-10-01) · Progress Toward Restoring the Everglades: The Tenth Biennial Review - 2024: “highlights significant recent restoration progress” National Academies of Sciences, Engineering, and Medicine

Who gained

Money that reached nature, beside money that stayed elsewhere.

Reached nature or the ground

Not published
No figure published.

Gained elsewhere

Not totalled
Currency: USD · Window: Mixed — see each line. Figures cover different periods and are not compared as a ratio. * Estimate built from cited figures.

Responses on record

  • US Army Corps of Engineers (2000; 2025): In 2000 the Corps' estimate was US$7.8 billion; GAO recommended that it add a means of reporting cumulative cost changes. CRS recorded in 2025 that the Corps has specified that no federal investment in CEPP North infrastructure can occur until the phosphorus effluent limit is met. · US General Accounting Office (now GAO)
  • State of Florida (14 January 2025): CRS recorded that the state is proceeding with CEPP North construction before an attainment determination and expects its projects to be operational by the end of 2025. · Congressional Research Service

In court and with insurers

Every proceeding and every insurer decision on record.

Lawsuits and rulings

No court case on record. No court has ruled on this case.

Insurers

No insurer decision on record.

What nature saw

Outcomes measured on the ground, and nature's note.

Nature's report opens this page. Below: further outcomes measured on the ground.

Projects complete
One CERP project and two major components (2024)
National Academies tenth review summary; six CERP projects under construction
Melaleuca-dominated area
75 percent reduction
National Academies tenth review summary; Melaleuca eradication project
Stormwater treatment areas meeting the phosphorus limit
Only STA-3/4
National Academies tenth review summary; outflow phosphorus concentrations trending downward
Central reporting of restoration outcomes
None
National Academies tenth review summary: no centralized multi-agency reporting mechanism

What we don't know

Undisclosed, unproven, untried: recorded as data.

Nature

  • Not measured Harm to nature: The record holds no measurement of harm to nature.
  • Disputed Whether construction should proceed before the phosphorus limit is met

Accounts

  • Disputed How much the plan costs and how long it takes

Record

  • None on record None on record: a system-wide measurement of ecological recovery attributable to CERP. The National Academies summary reports project-level results (Melaleuca, phosphorus in stormwater treatment areas) and no centralized multi-agency reporting mechanism.
  • None on record None on record: dollar totals and project counts in the tenth review's summary; the summary gives no dollar amounts.
  • Unclear Disputed: the cost of the plan, given as US$7.8 billion (GAO, 2000), US$8.2 billion (1999 and FY 2000 dollars) and US$23.2 billion (FY 2020 dollars). CRS wrote that the spending figures are nominal and the estimates use different base years, so they are not directly comparable.
  • Disputed Disputed: sequencing on the northern Everglades project. The Corps specified that no federal investment in CEPP North infrastructure can occur until the phosphorus effluent limit is met; Florida is proceeding with CEPP North construction before an attainment determination (CRS, 2025).
  • None on record Not yet determined: attainment of the phosphorus effluent limit; assessment is required to begin in 2026.

Did the harm stop?

The sources reviewed do not report that the degradation of the ecosystem has stopped. The National Academies summary reports progress on projects and phosphorus trends in stormwater treatment areas, and the tenth review describes the Everglades as "dramatically degraded" in water quality, quantity, flow and distribution.

Who paid?

Costs are shared between the federal government and the State of Florida: through FY 2024 the federal government spent US$3.2 billion and Florida US$2.8 billion on CERP construction projects, and the federal government spent approximately US$1.0 billion on non-CERP construction (CRS, nominal dollars).

Sources

Voices on record: — Company or project✓ Government and regulators— Courts— Press and investigations— Communities and civil society— Researchers

Connected cases

Related matters, and cases linked to this one through the same organisations, with the role each played in both.

Science and environment

PFOA (C8) and PFAS
PFAS are a large family of human-made chemicals that persist in the environment and the body; PFOA, also called C8, is one of them and was used to make Teflon.
Agriculture, livestock and food · Water use · Chemical pollution · Protected area / relocation · Netherlands · 1990–2026
Dutch nitrogen crisis and farm buyouts
Same type: Water use, Protected area / relocationHarm to nature disputedHarm to nature not measured
Protected area / relocation · Water use · Kenya · 2014–2024
Sengwer evictions from Embobut forest and the EU Water Towers programme (Kenya)
Same type: Protected area / relocation, Water useHarm to nature disputedHarm to nature not measured
Urban greening and displacement · Protected area / relocation · Water use · India · 2015–2024
Chennai water-body restoration evictions and Perumbakkam resettlement
Same type: Protected area / relocation, Water useHarm to nature disputedHarm to nature not measured
Protected area / relocation · Water use · Uzbekistan · 2024–2026
Sea Breeze resort on the Charvak reservoir, Uzbekistan
Same type: Protected area / relocation, Water useHarm to nature disputedHarm to nature not measured
Insurance, liability and compensation funds · Protected area / relocation · Water use · Global · 1991–2026
Global Environment Facility Trust Fund: replenishments and independent evaluation
Same type: Protected area / relocation, Water useHarm to nature disputedHarm to nature not measured
Finance, funds and markets · Protected area / relocation · Water use · Global · 2020–2026
Global Fund for Coral Reefs (GFCR)
Same type: Protected area / relocation, Water useHarm to nature disputedHarm to nature not measured