Who gains from saving nature
Ledger 1 : 33 — For each dollar financing nature-based solutions in 2023, about $33 financed activities harmful to nature. (UNEP)
Cases / Data centre · Malaysia / Indonesia / Singapore · 2019–2026

Johor and Batam data centres for Singapore

Nature's voice · report
No measurement of the harm done to me here is on record.
Did nature suffer? Not measured. Disputed
What the record lacks: 3 none on record · 1 insufficient · 1 not measured · 1 disputed · 1 unclear See the gaps
Accounts of the harm differ
Is the water shortage in Nongsa caused by drought or by data centre demand?
  • Government and regulators BP Batam: Attributes the shortage to El Niño.
  • Press and investigations The Star (Jakarta Post/ANN): Residents had no piped water for three to six months while data centres were supplied from a separate reservoir through a dedicated pipeline. The Star (Jakarta Post/ANN)

After Singapore limited new data centre capacity, planned capacity grew in neighbouring Johor (Malaysia) and Batam (Indonesia). Johor paused approvals of water-intensive facilities in November 2025, and residents of Batam's Nongsa area, without piped water for three to six months, blocked the road to a data centre park in October 2026.

2,486 MW vs 207 MWPlanned data centre capacity, Johor vs Singapore
Fitch, as reported by TechNode Global, 28 August 2026. Planned capacity, not installed capacity.

Status As of October 2026: Nongsa residents blocked the road to a data centre park; Johor's pause on water-intensive approvals continued; no legal proceedings found.

What?
Data centre capacity planned for Johor and Batam as Singapore limited its own, with reported water shortages in Batam's Nongsa area. TechNode Global
Where?
Johor (Malaysia), Batam and Nongsa (Indonesia), Singapore.
When?
2019 to October 2026.
Who?
Gained
None on record
Lost
Harmed
Why?
Singapore's constraints on capacity steered growth to Malaysia, according to Fitch. TechNode Global
How?
Planned capacity in Johor was reported at 2,486 MW against 207 MW in Singapore; in Batam, data centres were supplied from a separate reservoir by dedicated pipeline. The Star (Jakarta Post/ANN)
6 of 6 questions answered from the record

What happened

The record, in order.

Singapore placed a moratorium on new data centres from 2019 to 2022 and kept a strict quota afterwards, according to the record reviewed. In August 2026 Fitch said that Singapore's capacity constraints were steering data centre growth to Malaysia, and put planned capacity at 2,486 MW in Johor against 207 MW in Singapore.

In Johor, the state paused approvals of water-intensive Tier 1 and Tier 2 data centres in November 2025, and deferred their water requests for evaporative cooling to 2027, W.Media reported in May 2026. Moody's projected in September 2026 that data centre demand in Malaysia would reach about 73 TWh by 2035, requiring 14 to 17 GW of capacity on top of 28 GW existing, with gas remaining a transition fuel. Wood Mackenzie projected that data centres could account for about 40 per cent of Johor's electricity demand by 2035.

In Batam, Indonesia, residents of the Nongsa area told The Star (via the Jakarta Post and ANN) in October 2026 that they had been without piped water for three to six months; on 8 October 2026 they blocked the road to a data centre park. The same report said the data centres were supplied from a separate reservoir through a dedicated pipeline.

Katadata reported that nine data centres in Nongsa would request 29 million litres of water a day in 2032, about 8.4 per cent of Batam's supply, and that a request of 1.4 trillion rupiah for repairs to the water network had been rejected by the central government. Batam's authority has linked the shortage to El Niño; whether drought or data centre demand is responsible is disputed in the coverage reviewed.

  1. 2019Singapore moratorium on new data centres begins (to 2022); strict quota follows
  2. 2025Johor pauses approval of water-intensive Tier 1–2 data centres (November)
  3. 2026Fitch: 2,486 MW planned in Johor vs 207 MW in Singapore (August); Moody's and Wood Mackenzie projections (June–September); Nongsa residents block road to data centre park (8 October)

What was said

Claims, in the words of those who made them.

Where accounts differ

Each party's account, side by side, with its source. The record does not settle these points; it shows them.

Is the water shortage in Nongsa caused by drought or by data centre demand?
Government and regulators
BP Batam

Attributes the shortage to El Niño.

Press and investigations
The Star (Jakarta Post/ANN)

Residents had no piped water for three to six months while data centres were supplied from a separate reservoir through a dedicated pipeline.

The Star (Jakarta Post/ANN)

How it looked

What was shown, beside what was recorded.

Shown

  • A 'green data centre' framework for Singapore, announced alongside the moratorium and quota.
    Government of Singapore

Recorded

  • Planned data centre capacity: 2,486 MW in Johor, 207 MW in Singapore (Fitch).
  • Johor paused approvals of water-intensive Tier 1–2 data centres in November 2025; their evaporative-cooling water requests were deferred to 2027.
  • Nongsa residents without piped water for three to six months; data centres supplied from a separate reservoir by dedicated pipeline.
  • Nine Nongsa data centres projected to request 29 million litres a day in 2032, about 8.4% of Batam's supply; a 1.4 trillion rupiah repair request was rejected by the central government.

Who gained

Money that reached nature, beside money that stayed elsewhere.

Reached nature or the ground

Not published
No figure published.

Gained elsewhere

Not totalled
Currency: · Window: . All figures cover the same period. * Estimate built from cited figures.

Responses on record

  • bp-batam (2025–2026): Attributes the water shortage to El Niño, according to the coverage reviewed.

In court and with insurers

Every proceeding and every insurer decision on record.

Lawsuits and rulings

No court case on record. No court has ruled on this case.

Insurers

No insurer decision on record.

What nature saw

Outcomes measured on the ground, and nature's note.

Nature's report opens this page. Below: further outcomes measured on the ground.

Planned capacity
2,486 MW vs 207 MW
Johor vs Singapore (Fitch, August 2026)
Projected data centre water request, Nongsa
29 million litres a day
Nine data centres, 2032; about 8.4% of Batam supply (Katadata)
Residents without piped water
3–6 months
Nongsa, Batam, as of October 2026 (The Star)

What we don't know

Undisclosed, unproven, untried: recorded as data.

Nature

  • Not measured Harm to nature: The record holds no measurement of harm to nature.
  • Disputed Is the water shortage in Nongsa caused by drought or by data centre demand?

Court

Record

  • Unclear Whether the shortage in Nongsa is caused by drought or by data centre demand: Batam's authority points to El Niño, and the coverage reviewed does not settle the attribution.
  • Insufficient Reported but not independently verified: a demand of 440 MLD for data centres on Johor's water operator by 2035 (about 23% of 2023 demand) and a tariff of RM5.33 per cubic metre for data centres, which come of a report in The Vibes.
  • None on record No ecological assessment of water withdrawals for the Johor or Batam data centres is cited in the sources reviewed.
  • None on record No court case, penalty or ruling is reported in the sources reviewed.

Did the harm stop?

Not on record: the sources reviewed describe the protest of October 2026 and do not report a halt to Batam's data centre expansion. Johor paused approvals of water-intensive facilities in November 2025.

Who paid?

Residents of Nongsa, who were reported without piped water for three to six months while the data centres were supplied through a dedicated line.

Sources

Voices on record: — Company or project— Government and regulators— Courts✓ Press and investigations— Communities and civil society— Researchers

Connected cases

Related matters, and cases linked to this one through the same organisations, with the role each played in both.

Science and environment

Air cooling and evaporative cooling
Two ways of cooling data centres: evaporative systems consume water, air cooling uses far less water but more electricity.
IPCC Tier 1
The simplest method in the IPCC guidelines for greenhouse-gas inventories, using default values per forest type when local measurements are not available.