Google data centre, Canelones (Uruguay)
- The record does not name which of my species, waters, soils or forests were harmed.
Google's original design for a data centre in Canelones foresaw about 7.6 million litres of drinking water a day, at a time of drought. Uruguay approved a reformulated project: air-cooled, at about one third of the capacity.
Approved design at about one third of the original capacity.
- Google — Government approval in 2024 for a reformulated, air-cooled data centre in Canelones BNamericas
- Google — About two thirds of the originally planned capacity, under the approved design (the approved design has about one third of the original capacity) BNamericas
What happened
Google planned a data centre in the department of Canelones, Uruguay. The original design foresaw the use of about 7.6 million litres of drinking water a day for the site.
The plan was under discussion during Uruguay's 2023 water crisis. A report published by the Presidency in August 2023 documented the water deficit; bottled water was distributed tax-free.
In 2024 Uruguay approved a reformulated project. The data centre would be air-cooled and would have about one third of the originally planned capacity.
Air cooling reduces water drawn on site but raises electricity use, which moves part of the water demand to power generation. In the United States, indirect water use linked to the grid has been estimated at about 12 times the direct water use of data centres; among the largest operators only Meta reports indirect water.
- 2023Water crisis; Presidency report on the water deficit (Aug)
- 2024Uruguay approves reformulated project: air-cooled, about one third of capacity
How it looked
Shown
- A new Google data centre in Uruguay
- Approved after reformulation to air cooling
Recorded
- Original design: about 7.6 million litres of drinking water a day
- Planned during a national water crisis
- Approved design: air cooling, about one third of the capacity
- Air cooling shifts water demand to electricity generation; the indirect share is not reported by Google
Who gained
Reached nature or the ground
Gained elsewhere
In court and with insurers
Lawsuits and rulings
- 2024Claimant wonApproval of Google's reformulated Canelones data centreGovernment of Uruguay (environmental authorisation) · Regulatory · Google (applicant) →
Uruguay approved a reformulated project using air cooling and about one third of the originally planned capacity. BNamericas
Insurers
What nature saw
Nature's report opens this page. Below: further outcomes measured on the ground.
What we don't know
Nature
- Not measured Harm to nature: The record holds no measurement of harm to nature.
Money
- None on record Investment value of the project — Not in the source record.
Record
- Not disclosed The electricity demand of the approved design and the water used to generate it: not published.
- None on record The original approval history and which authority approved the reformulated design: not detailed in the source record.
- None on record The source record gives the same daily figure (7.6 million litres) for Google's Uruguayan and Chilean projects; the figure has not been cross-checked against permit documents.
Did the harm stop?
The approved design uses air cooling instead of drinking water. Part of the water demand moves to electricity generation.
Who paid?
Not quantified.
Sources
Government and regulators
- Informe de déficit hídricoPresidencia de la República, Uruguay · 2023-08-23
Press and investigations
- Uruguay approves reformulated Google datacenter projectBNamericas · 2024
- Data centers' hidden water footprint is linked to the gridLatitude Media · 2026-08-25
- Big Tech's data centre push will take water from the world's driest areasSourceMaterial · 2025-04-09
Connected cases
- Andhra Pradesh granted Google-linked data centre incentives in October 2025 India · 2025
- Google (Company) — here: Project developer; there: Company the report describes as linked to the recipient
- Big Tech data-centre emissions accounting (Microsoft, Google, Amazon, Meta) United States · 2007–2026
- Google (Company) — here: Project developer; there: Company; reports hourly and annual carbon-free energy matching
- Deep-sea mining: TMC, NORI, the NOAA permit and the ISA International waters (Pacific Ocean) · 2022–2026
- Google (Company) — here: Project developer; there: Pledged not to source deep-sea minerals (2021)
- Google data centre, Cerrillos (Chile) Chile · 2024
- Google (Company) — here: Project developer; there: Project developer
- Quilicura data centres draw about 1.5 billion litres a year; wetland largely dried Chile · 2024
- Google (Company) — here: Project developer; there: Holder of a water withdrawal right