Barro Blanco hydro dam (Panama)
A 28.8 MW hydroelectric dam in Panama was registered under the UN Clean Development Mechanism and financed with USD 50 million in loans from FMO and DEG. An independent complaints panel found that the two banks had breached their own policies, and Panama withdrew the UN registration in November 2016.
USD 25 million from each lender. The 28.8 MW dam was registered under the UN Clean Development Mechanism; Panama withdrew the registration in November 2016.
Status As of the latest record: the dam stands, the UN CDM registration was withdrawn in 2016, the lenders published a management response in 2022, and a reported 2025 agreement is unverified.
- Ngäbe people — Homes, a school and cultural sites flooded in 2016
What happened
Barro Blanco is a 28.8 MW hydroelectric dam in Panama, described in the record as GENISA's dam. FMO, the Dutch development bank, and DEG, a German lender, each lent USD 25 million, USD 50 million in total. The project was registered under the Clean Development Mechanism (CDM), the UN system that gives carbon credits to projects in developing countries.
According to the research record, the dam flooded the homes, a school and cultural sites of the Ngäbe people in 2016. An independent complaints panel that examined the FMO and DEG loan found that the banks had breached their own policies.
In November 2016 Panama withdrew the project's UN CDM registration. Carbon Market Watch published a statement on the decision on 10 November 2016, and the research record describes it as the first such withdrawal by a host country. The dam remains in place. In 2022 the financiers published a management response to a third monitoring report on the project (Spanish-language version).
- 2016The CDM-registered dam floods Ngäbe homes, a school and cultural sites (as recorded). Panama withdraws the project's UN CDM registration (November); Carbon Market Watch issues a statement (10 November).
- 2022FMO and DEG publish a management response to the third monitoring report on Barro Blanco.
How it looked
Shown
- A 28.8 MW hydroelectric dam registered under the UN Clean Development Mechanism.UN CDM registration, as reported in the sources reviewed
Recorded
- FMO and DEG each lent USD 25 million to the project.
- An independent complaints panel found that the lenders had breached their own policies.
- In 2016 the dam flooded the homes, a school and cultural sites of the Ngäbe people.
- Panama withdrew the project's UN CDM registration in November 2016; Carbon Market Watch published a statement on the decision on 10 November 2016.
- The financiers published a management response to the third monitoring report on Barro Blanco in 2022 (Spanish-language version).
Who gained
Reached nature or the ground
Gained elsewhere
Responses on record
- FMO and DEG (2022): Published a management response to the third monitoring report on Barro Blanco (Spanish-language version). · DEG
In court and with insurers
Lawsuits and rulings
- Claimant wonIndependent complaints panel review of the FMO and DEG loan to Barro BlancoIndependent complaints panel of the lenders · Administrative · Complainants (not named) → FMO and DEG
The panel found that the lenders had breached their own policies.
Insurers
What nature saw
Nature's report opens this page. Below: further outcomes measured on the ground.
What we don't know
Nature
- Not measured Harm to nature: The record holds no measurement of harm to nature.
Record
- Insufficient Reported but not independently verified: deaths during protests by the Ngäbe in 2012.
- Insufficient Reported but not independently verified: an agreement covering part of the redress was signed in 2025.
Did the harm stop?
The dam remains in place. Panama withdrew its UN CDM registration in November 2016.
Who paid?
The record shows that homes, a school and cultural sites of the Ngäbe people were flooded. An agreement covering part of the redress is reported for 2025 but is not independently verified.
Sources
Company or project
Communities and civil society
- Press statement: Panama withdraws UN registration for Barro Blanco hydrodam projectCarbon Market Watch · 2016-11-10
Connected cases
- Berta Cáceres killing and Agua Zarca dam Honduras · 2013–2026
- FMO (Dutch development bank) (Bank) — here: Lender (USD 25 million); there: Financier (Dutch development bank)
- Corio, ABP and forest land investments (Netherlands) Netherlands · 2000–2021
- FMO (Dutch development bank) (Bank) — here: Lender (USD 25 million); there: Dutch development bank, 51% state-owned
- Dutch bank FMO backed a 20,000-hectare Sierra Leone sugar cane lease Sierra Leone · 2008–2015
- FMO (Dutch development bank) (Bank) — here: Lender (USD 25 million); there: Dutch development bank; partner in the Addax lease, withdrew around 2015
- European development banks financed Feronia palm plantations in Congo Democratic Republic of the Congo · 2013–2019
- FMO (Dutch development bank) (Bank) — here: Lender (USD 25 million); there: Development bank that invested in the plantations
- Panama moves 1,351 people off Gardi Sugdub island to the mainland Panama · 2008–2024
- GENISA (Company) — here: Dam developer; there: Developer of the Barro Blanco dam