Who gains from saving nature
Ledger 1 : 33 — For each dollar financing nature-based solutions in 2023, about $33 financed activities harmful to nature. (UNEP)
Cases / Chemical pollution · India · 2000–2024

Plachimada Coca-Cola plant (India)

Nature's voice · report
About 500,000 litres of water a day were drawn at Plachimada.
Did nature suffer? Yes. Harm is on record.
Recorded
  • Sludge containing cadmium was distributed as fertiliser. Down To Earth
What the record lacks: 3 none on record See the gaps

A Kerala commission assessed compensation of Rs 216 crore against Hindustan Coca-Cola for groundwater withdrawal and the distribution of cadmium-containing sludge as fertiliser at Plachimada. Down To Earth later reported that the compensation had not been paid.

Rs 216.26 crore vs 0Compensation assessed vs paid
As reported: the Kerala commission assessed the amount in 2010; Down To Earth reported none paid. the sources reviewed give no exact date for the last check.

Status As of the latest research: a 2010 Kerala commission finding of Rs 216.26 crore compensation; Down To Earth reported it unpaid; no payment recorded.

What?
A Kerala commission assessed Rs 216 crore of compensation against Hindustan Coca-Cola over groundwater withdrawal and cadmium-containing sludge distributed as fertiliser at Plachimada; the compensation was reported unpaid. Down To Earth
Where?
Plachimada, Kerala, India. Down To Earth
When?
The record spans 2000–2024; the plant closed in 2004 and the commission finding dates from 2010. Down To Earth
Who?
Gained
  • Hindustan Coca-Cola — Operated the beverage plant that drew groundwater at Plachimada; its earnings from the plant are not documented in the record. Down To Earth
Lost
  • Villagers of Plachimada — The assessed compensation was not paid to them. Down To Earth
Harmed
  • Groundwater and farmland at Plachimada — About 500,000 litres of water a day were drawn; cadmium-containing sludge was distributed as fertiliser. Down To Earth
Why?
The record does not state a reason; the activity was beverage production.
How?
By withdrawing groundwater at about 500,000 litres a day and by distributing cadmium-containing sludge as fertiliser. Down To Earth
6 of 6 questions answered from the record

What happened

The record, in order.

The record covers a beverage plant of Hindustan Coca-Cola at Plachimada, India, for the period 2000–2024. It concerns two matters: the withdrawal of groundwater and the distribution of sludge containing cadmium as fertiliser.

Down To Earth, citing a Kerala expert committee, reported that about 500,000 litres of water a day were drawn at Plachimada.

In 2010 a Kerala commission found that Hindustan Coca-Cola should pay compensation of Rs 216 crore (given elsewhere as Rs 216.26 crore) at Plachimada. Down To Earth reported at the time that cadmium-containing sludge had been distributed as fertiliser.

The Coca-Cola plant at Plachimada closed in 2004, according to Down To Earth. In a later report, which the research dates to about 2022 and associates with a 2010–2023 span, Down To Earth stated that the damage had been established but the compensation had not been paid. The research records the amount paid as zero and records no data on any personal penalty.

  1. 2004The Coca-Cola plant at Plachimada closed
  2. 2010A Kerala commission found Hindustan Coca-Cola should pay Rs 216 crore (given elsewhere as Rs 216.26 crore); cadmium-containing sludge had been distributed as fertiliser
  3. 2022Down To Earth reported that Plachimada was still awaiting the compensation (date approximate)

How it looked

What was shown, beside what was recorded.

Shown

    Recorded

    • A Kerala commission found in 2010 that Hindustan Coca-Cola should pay Rs 216 crore (given elsewhere as Rs 216.26 crore) in compensation at Plachimada.
    • Cadmium-containing sludge had been distributed as fertiliser.
    • About 500,000 litres of water a day were drawn at Plachimada (Down To Earth, citing a Kerala expert committee).
    • The plant closed in 2004; the damage identified was not paid for (Down To Earth).
    • Compensation paid, according to the sources reviewed: zero.

    Who gained

    Money that reached nature, beside money that stayed elsewhere.

    Reached nature or the ground

    0m
    Compensation paid to date0m
    Rs 216.26 crore (about INR 2,163 million) was assessed in 2010; the research records zero paid.

    Gained elsewhere

    Not totalled
    Reached the ground
    0m
    Currency: INR · Window: 2000–2024. All figures cover the same period. * Estimate built from cited figures.

    In court and with insurers

    Every proceeding and every insurer decision on record.

    Lawsuits and rulings

    1. 2010Claimant wonINR 2162600bn Rs 216.26 crore assessed; none paid
      Kerala commission finding on compensation at Plachimada
      Kerala commission (described elsewhere as an expert committee) · Administrative · Not stated in the record; the research names the villagers as those who bore the loss → Hindustan Coca-Cola

      A state commission found that the company should pay Rs 216 crore (given elsewhere as Rs 216.26 crore); the cadmium-containing sludge had been distributed as fertiliser. The sources reviewed record zero paid and no court route. Down To Earth

    Insurers

    No insurer decision on record.

    What nature saw

    Outcomes measured on the ground, and nature's note.

    Nature's report opens this page. Below: further outcomes measured on the ground.

    Compensation assessed vs paid
    Rs 216.26 crore vs 0
    Kerala commission, 2010; Down To Earth on non-payment
    Groundwater drawn
    About 500,000 litres a day
    Down To Earth, citing a Kerala expert committee
    Sludge
    Cadmium-containing
    Distributed as fertiliser (Down To Earth, 2010)

    What we don't know

    Undisclosed, unproven, untried: recorded as data.

    Record

    • None on record Earnings of Hindustan Coca-Cola from the Plachimada plant: not documented in the record.
    • None on record Personal penalty for any individual: no data in the record.
    • None on record Payment: the research records zero paid against Rs 216.26 crore assessed; no payment date or later figure is given.

    Did the harm stop?

    The plant closed in 2004 (Down To Earth). The compensation assessed in 2010 was recorded as unpaid in the latest report.

    Who paid?

    The research records the villagers as the ones who paid: the assessed compensation was not paid to them.

    Sources

    Voices on record: — Company or project— Government and regulators— Courts✓ Press and investigations— Communities and civil society— Researchers

    Press and investigations

    Science and environment

    Groundwater
    Water held underground in soil and rock, drawn through wells.