Cases / Data centre · United States · 2025

Louisiana regulators fast-track second batch of gas plants for Meta data center

Short record: the main facts, with sources. A full case file has not been prepared.

Nature's voice · report
No measurement of the harm done to me here is on record.
Did nature suffer? Not measured.
What the record lacks: 3 none on record · 2 insufficient · 1 not measured See the gaps

Louisiana regulators approved three gas plants for Meta's Hyperion data center in 2025 and fast-tracked seven more in April 2026. As You Sow and partners reported that Meta's location-based Scope 2 emissions rose about 150 percent from 2019 to 2024.

What?
Louisiana regulators approved gas plants to power Meta's Hyperion data center and fast-tracked a second group in April 2026, WWNO reported. WWNO
Where?
Louisiana, United States WWNO
When?
Three plants approved in 2025; seven more fast-tracked in April 2026, as reported by WWNO on 21 April 2026. WWNO
Who?
Gained
  • Meta — Gas plants approved to supply its Hyperion data center WWNO
Lost
  • Louisiana ratepayers — WWNO's headline reports advocates citing rising costs and a lack of transparency WWNO
Harmed
Why?
The gas plants are to supply Meta's Hyperion data center; the sources reviewed do not state why gas power was chosen. WWNO
How?
The Louisiana PSC voted 4 to 1 to fast-track seven gas plants in April 2026, after approving three for Meta in 2025. WWNO
6 of 6 questions answered from the record

What happened

The record, in order.

WWNO reported that Louisiana regulators approved three gas plants, totaling 2.26 GW, for Meta in 2025.

WWNO reported that in April 2026 the Louisiana PSC fast-tracked seven more plants, about 5.2 GW, by a 4 to 1 vote.

As You Sow and partners said in a May 2026 SEC filing that Meta's location-based Scope 2 emissions rose about 150 percent between 2019 and 2024, and that Hyperion would involve 5 GW and seven new gas plants.

    In court and with insurers

    Every proceeding and every insurer decision on record.

    Lawsuits and rulings

    No court case on record. No court has ruled on this case.

    Insurers

    No insurer decision on record.

    What we don't know

    Undisclosed, unproven, untried: recorded as data.

    Nature

    • Not measured Harm to nature: The record holds no measurement of harm to nature.

    Record

    • Insufficient Reported but not verified: Meta describes the Hyperion supply as '100 percent clean'.
    • Insufficient Reported but not verified: Entergy's gas plants may enter the utility's rate base.
    • None on record The sources reviewed do not state how the cost of the gas plants is shared between Meta and Louisiana ratepayers.
    • None on record The 150 percent Scope 2 rise is a figure from an advocacy group, not from Meta's own reporting.
    • None on record The sources do not state the actual gas output or emissions of the Hyperion plants.

    Did the harm stop?

    Not stated in the sources reviewed.

    Who paid?

    Not stated in the sources reviewed.

    Sources

    Voices on record: — Company or project— Government and regulators— Courts✓ Press and investigations— Communities and civil society— Researchers

    Connected cases

    Related matters, and cases linked to this one through the same organisations, with the role each played in both.

    Institutions

    SEC
    The US Securities and Exchange Commission, which regulates securities markets and what companies tell investors.