Turkish court annulls Loç Valley hydropower approval; 117 villagers on trial
Short record: the main facts, with sources. A full case file has not been prepared.
A Turkish administrative court annulled the environmental approval for the Loç Valley hydropower plant in Cide for a second time in 2020, and the Council of State rejected the developer's objection. Bianet reported that 117 villagers had been on trial since 2012, and the valley's stream is at stake.
What happened
The Kastamonu Administrative Court annulled the environmental impact approval for the Loç Valley plant for a second time in April 2020, relying on an expert report, according to bianet.
The Council of State rejected the company's objection, bianet reported in 2020.
Bianet reported that 117 villagers had been on trial since 2012.
According to the sources reviewed, the impact approval was annulled in 2011 and again in 2020.
In court and with insurers
Lawsuits and rulings
- 2020Outcome not on recordLoç Valley hydropower environmental approval, second annulmentKastamonu Administrative Court · Administrative · Not named in the sources reviewed → Not named in the sources reviewed
Annulled the environmental impact approval for the plant a second time, relying on an expert report. bianet
- 2020Outcome not on recordLoç Valley hydropower objection before the Council of StateCouncil of State (Danıştay) · Administrative · Not named in the sources reviewed → Not named in the sources reviewed
Council of State rejected the company's objection, according to bianet (2020). bianet
Insurers
What we don't know
Nature
- Not measured Harm to nature: The record holds no measurement of harm to nature.
Court
Record
- None on record The sources reviewed also say the Council of State had earlier reversed a first annulment, but the date and sequence are not clear.
- Insufficient Reported but not verified: a 2011 KTÜ study that small hydropower construction harms stream water and fish stock; only a summary was available.
- Unclear Whether the plant is operating, and whether the required minimum environmental flow is kept, is not stated; no national compliance measurement was found.
- None on record The developer and its owners are not named in the sources reviewed.
- None on record The outcome of the case against the villagers is not stated in the sources reviewed.
Did the harm stop?
Not stated in the sources reviewed.
Who paid?
Not stated in the sources reviewed.
Sources
Press and investigations
Connected cases
- Council of State lets 60 informal neighbourhoods stay in Bogotá reserve buffer Colombia · 2013
- Council of State (Danıştay) (Court) — here: Rejected the company's objection; there: Court that issued the ruling
- Court annuls environmental approval for Loç Valley hydropower plant a second time Turkey · 2011–2020
- Kastamonu Administrative Court (Court) — here: Annulled the environmental approval; there: Court that annulled the EIA approval for a second time
- Çeşme wind farm olive grove partly registered to Treasury despite 2014 halt Turkey · 2013–2014
- Council of State (Danıştay) (Court) — here: Rejected the company's objection; there: Stayed the expropriation in 2014
- European court found Turkish permit for Bergama cyanide gold mine breached privacy Turkey · 2004
- Council of State (Danıştay) (Court) — here: Rejected the company's objection; there: Annulled the permit; the mine was reported to keep operating
- Milas–Yatağan olive groves opened to mining (Law 7554, temporary article 45) Turkey · 2022–2026
- Council of State (Danıştay) (Court) — here: Rejected the company's objection; there: Council of State; annulled 2022 regulation amendment; stayed execution for about 194 parcels