EDF's planned 300 MW wind farm on Zapotec common land in Oaxaca had its contracts cancelled in June 2022 after a community lawsuit. The case shows how common land rights can decide the fate of large renewable developments.
- Unión Hidalgo Zapotek community — Won the cancellation of the wind farm contracts on its common land ProDESC
- EDF — Wind farm contracts cancelled; a community lawsuit against it in France is listed as ongoing
What happened
The 115-turbine, 300 MW Gunaa Sicarú wind farm, which France's EDF planned on Zapotek community land in Oaxaca, was cancelled in June 2022, according to ProDESC.
ProDESC reported that the Zapotek community of Unión Hidalgo obtained court measures and that the cancellation was definitive.
The community also brought a lawsuit against EDF in France, which the sources list as ongoing.
Electricity and connection contracts with CFE, the Mexican state electricity company, were cancelled.
In court and with insurers
Lawsuits and rulings
- 2022-06-02Claimant wonUnión Hidalgo community challenge to the Gunaa Sicarú wind farmMexican court (not named in the sources reviewed) · Civil · Unión Hidalgo Zapotek community → Not named in the sources reviewed
The community obtained court measures, and ProDESC reported that the cancellation of the wind farm was definitive. ProDESC
- OngoingUnión Hidalgo community lawsuit against EDFFrench court (not named in the sources reviewed) · Civil · Unión Hidalgo Zapotek community → EDF
Listed among ongoing cases in the sources reviewed; no further details are given.
Insurers
What we don't know
Nature
- Not measured Harm to nature: The record holds no measurement of harm to nature.
Record
- Insufficient Reported but not verified: the previous government's policy favouring the state utility CFE may have played a role in the cancellation.
- None on record The sources reviewed do not give the outcome of the French lawsuit.
- None on record The sources reviewed do not state the wind farm's environmental impacts.
Did the harm stop?
Not stated in the sources reviewed.
Who paid?
Not stated in the sources reviewed.
Sources
Communities and civil society
Connected cases
- EDF spying on Greenpeace (France) France · 2011–2013
- Électricité de France (Company) — here: Developer of the planned wind farm; there: Defendant; French utility
- Isthmus of Tehuantepec wind farms, including Mareña, faced local opposition Mexico · 2012–2022
- Électricité de France (Company) — here: Developer of the planned wind farm; there: Developer of the Gunaa Sicarú wind farm
- Samir Flores murder and the Huexca power plant Mexico · 2019