Port and channel dredging on the Caspian after the fall in water level: Kazakhstan, Azerbaijan and Russia
- The record does not name which of my species, waters, soils or forests were harmed.
Falling water forced dredging at Caspian ports and shipping channels. The Astana Times (13 October 2026) reported the Aktau port dredging project at 20.6 billion tenge; the Times of Central Asia (9 September 2026) listed about US$56.8 million for Kuryk, US$39.8 million for Aktau and US$17.6 million for Bautino. Azerbaijan and Russia reported volumes dredged without costs.
Astana Times, 13 October 2026, which gives US$45.6 million alongside; the Times of Central Asia (9 September 2026) gives about US$39.8 million for Aktau dredging.
Status As of October 2026: Kuryk dredging was completed in November 2024; the main Aktau phase began in October 2026 for completion at the end of 2026; costs are given for Kazakhstan only and differ between sources.
- Jan De Nul Kazakhstan LLP — General contractor for the Kuryk dredging completed in November 2024; contract value not on record Kazakhstan Temir Zholy
- China Harbour Engineering Company — General contractor for the 2026 Aktau dredging, per the Astana Times; contract value not on record The Astana Times
- Rosmorport — State agency carrying out the Volga-Caspian canal dredging; budget not on record Ports Europe
- Shipping operators using Kazakh ports — Ferries carried only 80% of a full cargo load from Kazakhstan; re-berthing of grain vessels at Aktau cost about 1 million tenge per ship (Astana Times) The Times of Central Asia
- Baku International Sea Port — Dubendi oil terminal throughput fell to 810,000 tons in the first half of 2025 from 880,000 tons; its director linked this to the water level Baird Maritime (Reuters)
What happened
Court et al. (Communications Earth & Environment, 10 April 2025) wrote that access to the Caspian from the Volga could be compromised by a decline of as little as 5 m, "with dredging already implemented to keep passage for larger vessels open", that operators of offshore oil facilities in the northern Caspian "are dredging channels to maintain shipping logistics", and that operations at Aktau port and a desalination plant intake had been disrupted by declining water levels. Kazakhstan's Transport Minister Marat Karabaev said in December 2023, according to Ports Europe, that urgent dredging at Kuryk would be completed by July 2024. Kazakhstan Temir Zholy announced on 21 November 2024 that Kuryk dredging had finished ahead of schedule, with over 990,000 cubic metres removed in four months by Jan De Nul Kazakhstan LLP and a depth of 7 to 8 m in the port and approach channel; no cost was stated.
Aktau port dredging began in 2025. The Times of Central Asia reported on 12 May 2025, crediting gov.kz, that the port would be deepened by 1.5 to 2 m with Jan De Nul equipment, to finish in the fourth quarter of 2025. The Astana Times reported on 13 October 2026 that the port administration gave the project as 20.6 billion tenge (US$45.6 million), financed by the Kazakh government and Ministry of Transport partly through loans, covering 77.1 hectares of port waters and about 1.3 million cubic metres, with China Harbour Engineering Company as general contractor and depths rising from 4.5–5 m to 6–7 m; the main phase began in October 2026 and is scheduled to finish at the end of 2026. The port administration said reports of a French company's involvement were incorrect and expected maritime cargo transport costs to fall by approximately 10–15%. The Astana Times (10 January 2026) separately reported Aktau annual dredging costs of roughly 400 million tenge, re-berthing of grain vessels at about 1 million tenge per ship, and an average Aktau depth of 4.5 m against 6.5–7 m needed for full operations.
A second Kuryk project, deepening port waters and the approach channel to five metres, was reported by the Times of Central Asia on 24 December 2025 as fully financed by ERSAI, using its own dredger, with dredging planned for January to June 2026 and no cost disclosed. The Times of Central Asia (9 September 2026) wrote that "Kazakhstan's infrastructure plan puts the cost of the Kuryk dredging project at approximately $56.8 million", that around $39.8 million "has been allocated for dredging the port waters" at Aktau, that Bautino dredging was planned at around $17.6 million, and that another approximately $65.2 million was planned for Berth No. 12 reconstruction and Berth No. 3 extension; the article summed the projects listed at roughly $179 million. That article also gives Kuryk as 1.7 million cubic metres and 8.5 m, which differs from Kazakhstan Temir Zholy's November 2024 figures.
In Azerbaijan, Reuters reported on 21 August 2025 that more than 250,000 cubic metres were dredged at the Dubendi oil terminal in 2024, that oil and oil-product transport there fell to 810,000 tons in the first half of 2025 from 880,000 tons a year earlier, and that Baku International Sea Port director Eldar Salakhov linked the fall to the lower water level; a new dredger, the Engineer Soltan Kazimov, was due in service. No cost was given. In Russia, Ports Europe reported on 28 May 2025 that the state agency Rosmorport had removed about 1 million cubic metres from the Volga-Caspian Sea Shipping Canal since 2 April against a 7 million cubic metre target for 2025; no cost or stated reason appeared in the part of the article that could be read. For shipping, Alakbar Azizli of the Azerbaijan Caspian Shipping Company said at Baku Climate Action Week that one of the company's ferries could carry only 80% of a full cargo load from Kazakhstan.
- 2023Kazakhstan's Transport Minister says urgent dredging at Kuryk will finish by July 2024 (Ports Europe, 13 December)
- 2024Kuryk dredging completed (announced 21 November): over 990,000 m3, 7–8 m depth
- 2024More than 250,000 m3 dredged at Baku's Dubendi oil terminal (reported by Reuters, 21 August 2025)
- 2025Rosmorport begins 2025 dredging of the Volga-Caspian canal on 2 April against a 7 million m3 target
- 2025Aktau port deepening by 1.5 to 2 m starts (reported 12 May)
- 2025ERSAI Kuryk deepening to five metres reported as privately financed (24 December)
- 2026Aktau main dredging phase begins in October; completion scheduled for the end of 2026 (Astana Times, 13 October)
What was said
“with dredging already implemented to keep passage for larger vessels open”
“Kazakhstan's infrastructure plan puts the cost of the Kuryk dredging project at approximately $56.8 million”
“the cost of maritime cargo transportation is expected to decrease by approximately 10-15%”
“one of the company's ferries can now carry only 80% of a full cargo load from Kazakhstan”
Where accounts differ
Each party's account, side by side, with its source. The record does not settle these points; it shows them.
Over 990,000 m3 removed; depth 7 to 8 m in the port and approach channel.
Kazakhstan Temir ZholyOver 1.7 million m3 of soil removed and depth raised to 8.5 m.
The Times of Central Asia20.6 billion tenge (US$45.6 million); China Harbour Engineering Company is general contractor; reports of a French company's involvement were incorrect.
The Astana TimesAround $39.8 million allocated for dredging the port waters; Jan De Nul supplied the dredging equipment (May 2025).
The Times of Central AsiaHow it looked
Shown
- Kuryk dredging described as completed "in record time" to allow vessels to reach full load, expand terminal capacity and support the Trans-Caspian route.Kazakhstan Temir Zholy press service · Kazakhstan Temir Zholy
- Aktau dredging described as expected to cut maritime cargo transport costs by about 10–15% and raise Trans-Caspian cargo volumes by up to 30%.Aktau port administration, as reported by the Astana Times · The Astana Times
Recorded
- Kuryk: over 990,000 m3 removed in four months, 7–8 m depth (Kazakhstan Temir Zholy, 21 November 2024); cost not stated.
- Aktau: 20.6 billion tenge project, 77.1 hectares, about 1.3 million m3, depths 4.5–5 m to 6–7 m, main phase from October 2026 (Astana Times, 13 October 2026).
- Dubendi terminal (Baku): more than 250,000 m3 dredged in 2024; throughput 810,000 tons in the first half of 2025 against 880,000 tons (Reuters).
- Volga-Caspian Sea Shipping Canal: about 1 million m3 removed from 2 April to late May 2025 against a 7 million m3 target (Ports Europe).
- No source reviewed gives a cost for the Azerbaijani or Russian dredging, or states how much of the Kazakh port spending is due to the falling sea rather than to capacity expansion.
In nature's name
Money moved in nature's name
| What | Kind | Amount | Period |
|---|---|---|---|
| Aktau port dredging project, as stated by the port administration (20.6 billion tenge; the Astana Times also states US$45.6 million; the Times of Central Asia gives about US$39.8 million) Kazakh government and Ministry of Transport, partly through loans The Astana Times | Budget | 20.6bn KZT | 2025–2026 |
| Aktau port waters dredging, as allocated (no source named in the article; differs from the 20.6 billion tenge figure) Not stated The Times of Central Asia | Budget | $40m | not stated |
| Kuryk dredging project cost, per Kazakhstan's infrastructure plan (the 2024 completion announcement gave no cost) Not stated The Times of Central Asia | Budget | $57m | not stated |
| Bautino port dredging, planned (planned) Not stated The Times of Central Asia | Budget | $18m | planned |
| Reconstruction of Berth No. 12 and extension of Berth No. 3 at Aktau, planned (berth works rather than dredging; the sources reviewed do not say how much is due to the falling sea) Not stated The Times of Central Asia | Budget | $65m | planned |
| Aktau annual dredging costs (roughly 400 million tenge a year; the source also states US$782,870) Not stated The Astana Times | Spent | 400m KZT | annual |
Who gained
Reached nature or the ground
Gained elsewhere
Responses on record
- Kazakhstan Temir Zholy (21 November 2024): Announced Kuryk dredging completed ahead of schedule, with over 990,000 m3 removed and 7–8 m depth, to allow full loading and terminal expansion; gave no cost. · Kazakhstan Temir Zholy
- Aktau port administration (13 October 2026): Gave the dredging project as 20.6 billion tenge, said reports of a French company's involvement were incorrect, and expected cargo transport costs to fall by approximately 10–15%. · The Astana Times
- Baku International Sea Port (21 August 2025): Its director Eldar Salakhov linked lower Dubendi terminal throughput to the falling water level, which requires major dredging. · Baird Maritime (Reuters)
- Rosmorport (28 May 2025): Reported removing about 1 million m3 from the Volga-Caspian canal since 2 April 2025 against a 7 million m3 target; no further statement was read. · Ports Europe
In court and with insurers
Lawsuits and rulings
Insurers
What nature saw
Nature's report opens this page. Below: further outcomes measured on the ground.
What we don't know
Nature
- Not measured Harm to nature: The record holds no measurement of harm to nature.
Record
- None on record None on record in the sources reviewed: the cost of the Kuryk dredging completed in November 2024, the cost of the ERSAI Kuryk deepening, any cost for the Dubendi dredging, or any cost for Rosmorport's Volga-Caspian canal dredging.
- None on record None on record in the sources reviewed: the environmental effect of port dredging on the seabed or on sturgeon and seals; no impact assessment of the port projects was found.
- Disputed Disputed: Kuryk dredging. Kazakhstan Temir Zholy gave over 990,000 m3 and a depth of 7–8 m (November 2024); the Times of Central Asia (September 2026) gave 1.7 million m3 and 8.5 m.
- Disputed Disputed: Aktau dredging cost and contractor. The Astana Times gave 20.6 billion tenge (US$45.6 million) and China Harbour Engineering Company; the Times of Central Asia gave US$39.8 million (September 2026) and, in May 2025, Jan De Nul equipment. The Times of Central Asia gave annual dredging expenses at Aktau of roughly US$880,000, against roughly 400 million tenge (US$782,870) a year in the Astana Times.
- Unclear Unclear: how much of the roughly US$179 million total in the Times of Central Asia (the article's own sum, including a berth reconstruction) is due to the falling sea; the article does not apportion it.
- Insufficient Unconfirmed: Rosmorport dredging of about 10 million m3 in 2023 for a 4.5 m draft and a 98 cm fall in 2006–2013 appeared only in search excerpts.
Did the harm stop?
The sources reviewed show the spending continuing: the main Aktau dredging phase began in October 2026 and the level was still falling according to the declarations and press reports of 2025–2026.
Who paid?
For Aktau, the Astana Times reported the Kazakh government and Ministry of Transport, partly through loans; for the ERSAI Kuryk deepening, ERSAI itself; for Rosmorport's canal dredging, the state agency Rosmorport (cost not stated). Payers for Kuryk 2024 and for Azerbaijan's Dubendi dredging are not stated in the sources reviewed.
Sources
Company or project
- Dredging operations completed ahead of schedule at Kuryk port (press service)Kazakhstan Temir Zholy · 2024-11-21
Press and investigations
- Kazakhstan Launches Dredging Project to Expand Aktau Port on Key Trans-Caspian Corridor (Sergey Kwan; source credited to gov.kz)The Times of Central Asia · 2025-05-12
- Kazakhstan Deepens Kuryk Port on Trans-Caspian Transport Corridor (Sergey Kwan)The Times of Central Asia · 2025-12-24
- Aktau Port Dredging Project Aims to Cut Shipping Costs and Boost Cargo Capacity (Ayana Birbayeva)The Astana Times · 2026-10-13
- Shrinking Caspian Sea Raises the Cost of the Middle CorridorThe Times of Central Asia · 2026-09-09
- Caspian Sea's Decline Hits Economy, Infrastructure and Health (Laura Malikova, from Kazinform)The Astana Times · 2026-01-10
- Shallowing of Caspian Sea raises alarm in Azerbaijan (Reuters, Nailia Bagirova)Baird Maritime (Reuters) · 2025-08-21
- Rosmorport continues large-scale dredging works on Volga-Caspian canalPorts Europe · 2025-05-28
- Shrinking Caspian Sea forces Kazakhstan to dredge its portsPorts Europe · 2023-12-13
Researchers
- Rapid decline of Caspian Sea level threatens ecosystem integrity, biodiversity protection, and human infrastructure (Court et al., open-access copy)University of Leeds / White Rose Research Online · 2025-04-10
Connected cases
- Caspian Sea level decline: measured fall, modelled scenarios and disputed causes Caspian Sea (Azerbaijan, Iran, Kazakhstan, Russia, Turkmenistan) · 1995–2026 Related matter
- NCOC marine navigation channels to the Kashagan field, North Caspian (2021–2022) Kazakhstan · 2020–2022 Related matter